INSPECTION PROCEDURE 1. INSPECT TIE ROD END SUB-ASSEMBLY LH
(b) Install the nut to the stud bolt. (c) Flip the ball joint back and forth 5 times or more. (d) Using a torque wrench, turn the nut continuously at a rate of 3 to 5 seconds per turn and take the torque reading on the fifth turn. Standard turning torque: 1.0 to 3.9 N*m (10 to 40 kgf*cm, 9 to 34 in.*lbf) If turning torque is not within the specified range, replace the tie rod end LH. 2. INSPECT TIE ROD END SUB-ASSEMBLY RH HINT: Use the same procedures described for the LH side. |
Toyota Tundra Service Manual > Canister: Inspection
INSPECTION PROCEDURE 1. INSPECT CHARCOAL CANISTER ASSEMBLY (a) Visually check the charcoal canister assembly for cracks or damage. If cracks or damage are found, replace the charcoal canister assembly. (b) Check charcoal canister assembly operation. (1) With the purge port closed, blow 5 kPa (0.1 kg ...